BAE Systems
Construction of a class 1 nuclear structure.
Control Establishment, Survey Management, Piling, Asset Management, Training, Setting Out, Earthworks Volumes, As Built Surveys, BIM Modelling, Geotechnical Monitoring, Concrete Placement, Reinforcement.
Value
£200m+
Project Type
Nuclear
Client
BAE Systems
Year
2020
Barking Riverside
Construction of 1.5 kilometres of viaduct, a terminus station and installation of a new railway line, as well as modifying and realigning existing Network Rail operational infrastructure.
Control Establishment, Setting Out, Earthworks Volumes, Rail Surveys, As Builts, Machine Control.
Value
£196m
Project Type
Rail
Client
TfL
Year
2019
Stainton Aquaduct
Restoring of storm-damaged Stainton Aqueduct in South Cumbria, UK.
Control Establishment, Setting Out, As Built Drawings, Survey Management.
Value
£2.2m
Project Type
Aquaduct
Client
Kier
Year
2018
Christchurch Northern Corridor
Construction of a new four-lane motorway to connect the Northern Motorway to QEII Drive, Christchurch, NZ.
A first alliance of it’s size between the NZ Transport Agency, Christchurch City Council, Fulton Hogan, Aurecon and Jacobs in the south island.
Land Surveying, Control Establishment, Bulk Earthworks, Machine Control, Geotechnical Monitoring, Structural Monitoring & Roading.
Value
$290m
Project Type
Motorway
Client
NZTA
Year
2016
Midland Port
11 hectare inland port for receiving and storing containers close to State Highway 1, Christchurch, NZ.
Installation of 70,000 square metres of pavement, works included drainage, electricity and communications services, floodlighting, and a rail siding and crossings to connect to Lyttelton Port by rail.
Setting Out, Machine Control, As Built
Value
$24m
Project Type
Port
Client
Lyttelton Port Co. Ltd
Year
2016
Woodhouse Tunnel
Strengthening works to a vital piece of infrastructure, working purely at night. Leeds, UK
Concrete repairs, Drainage, Waterproofing, Reinforcement, Excavation, Painting, Concrete placing.
Value
£19m
Project Type
Tunnel
Client
Volker Laser
Year
2015